Piņon High School Athletic Fields
Piņon Unified School District #4
Piņon, Arizona Photos by: FCI

Owner: Piņon Unified School District #4

Project Architect:
Robert Pian
AIA, Partner Principal


Consultants:
Plateau Engineering, Inc.

Electrical Design Consultants, Inc.


General Contractor: FCI Constructors, Inc.

Cost: $3,814,744

Scheduling:
Design Start:
March 2001
Design Completion:
June 2001
Construction Start:
July 2001
Construction Completion:
February 2002


This project consisted of construction of a new football stadium, regulation soccer and baseball facilities with a state of the art Synthetic Turf system. A Microencapsulated impermeable track system, field lighting, and stadium seating were also constructed along with concession facilities to serve all three facilities.