Greenbrier Elementary School
Deer Valley Unified School District #97
| Glendale, Arizona |
Photos
by: Robert Pian |
|
Owner:
Deer Valley Unified School District #97
Project Architect:
Robert Pian AIA, Partner Principal
Consultants:
Lowry Sorrenson Wilkinson
Gookin Engineering, Inc.
R.E. Joachim and Associates, Inc.
Electrical Design Consultants, Inc.
E.M. Plummer Consulting Engineers
The Campbell Collaborative
Design-TEC Food Facilities, Inc.
General Contractor: Phase 1: N. L. Bouth Phase 2: Norquay
Size:
Phase 1: 29,000 SF Phase 2: 52,000 SF Total: 81,000 SF
Cost: Phase 1: $2,885,513 Phase 2: $5,400,000
Scheduling:
Phase 1:
Design Start: February 1994
Design Completion: August 1994
Construction Start: September 1994
Construction Completion: September 1995
Phase 2:
Design Start: April 1998
Design Completion: July 1998
Construction Start: August 1998
Construction Completion: September 1999
|
|
|
Greenbrier Elementary was an existing "portable" elementary campus, which remained in use
during the construction period. Phase 1, the "Core" facility, consisted of administration,
art, music, media center, and a divisible multipurpose cafeteria/stage facility. When building
construction was complete, the existing portables, which housed these functions, were relocated to
another campus as needed. The buildings are concrete masonry and metal deck roof. Although the
campus is a prototype design, it features a distinctive masonry block pattern, varying color schemes,
and a unique entry design. The design also incorporated relocation of existing equipment and furnishings.
Phase 2 included two detached classroom buildings and a classroom kindergarten wing, which allowed for
the removal of all remaining portable classrooms and construction of new playfields. Separate
kindergarten and primary play areas and apparatus, along with soccer fields, softball fields, dedicated
bus, parent drop-off and parking areas.
|
|