Copper Creek Elementary
Deer Valley Unified School District #97
| Glendale, Arizona |
Photos by: Mark Bosclair |
|
Owner:
Deer Valley Unified School District #97
Principal in Charge:
Donald Gadbery
AIA, Partner Principal
Robert Pian
AIA, Partner Principal
Project
Architect:
Howell Shay
AIA, Partner Principal
Team:
Howell Shay
AIA, Partner Principal
Consultants:
R. E. Joachim and Associates, Inc.
Gookin Engineering, Inc.
Electrical Design Consultants, Inc.
E.M. Plummer Consulting Engineers
The Campbell Collaborative
Design-TEC Food Facilities, Inc.
General Contractor: Target General, Inc.
Size:
91,636 SF
Cost: $8,068,795
Scheduling:
Design Start: July 1996
Design Completion: November 1996
Construction Start: December 1996
Construction Completion: August 1997
|
|
|
This new K-6, 850-student elementary school consists of a two story classroom wing, with
16 classrooms, toilet rooms, and teacher work areas at each floor level. The Multipurpose
Building consists of a food service facility and a large multipurpose room. The Multipurpose
Building also includes indoor and outdoor playgrounds and P.E. Classrooms that can be separated
from the main multipurpose area via operable partitions. Between the academic areas there is a
large interior courtyard, which is zoned and is provided with landscaped art patio, outdoor
teaching circles, a library patio and an amphitheater that backs up to the interior platform.
|
|