Chandler Christian Church
Chandler Christian Church
| Chandler, Arizona |
Photos by: Carlos Murrieta |
|
Owner:
Chandler Christian Church
Principal in Charge:
Terry Worcester
AIA, Partner Principal
Project
Architect:
Howell Shay
AIA, Partner Principal
Team:
Howell Shay
AIA, Partner Principal
Consultants:
General Contractor: MTV General Contractors
Size:
28,781 SF
Cost: $2,411,175
Scheduling:
Design Start: August 1996
Design Completion: March 1997
Construction Start: August 1997
Construction Completion: May 1998
|
|
|
Program
Phase one of facilities development was designed to master plan and anchor the improvements of a 23-acre
underdeveloped site on south Alma School Road in Chandler, Arizona.
The parking, landscape development and underground utility services were designed to facilitate significant growth
within a modest Phase one construction budget.
The building facilities of Phase one included a multipurpose,
400 person, 28,781 SF assembly area that featured a stage area
to accommodate a future seating area expansion. Classrooms, nursery
and administration spaces were organized on two levels to maximize
the use of site and building construction budget.
|
|